| Date of Meeting |
PIB or SC |
Administrative Department |
Enterprises |
Proposal |
Investment Approved (Rs. in Crore) |
|
04.08.2003
|
PIB
|
Industries
|
AGCL
|
Review on
completion of gas supply project to revamped BVFCL
|
Already approved on
20-01-2001
|
|
Modernization
of gas supply system from Duliajan to Lakwa via Namrup
|
49.67
|
|
WPT & BC
|
APTDC
|
Enhancement
of Govt. guarantee from Rs.4 Crore to Rs.30.00 Crore
|
Not approved
|
|
Power
|
ASEB
|
Approval of
R&M and PAGER schemes for NTPS
|
Not approved
|
|
11.12.2003
|
PIB
|
Industries
|
AGCL
|
Gas supply
project for consumers of Sibsagar, Jorhat & Golaghat
districts
|
100.00
|
|
Power
|
ASEB
|
Approval of
R&M and PAGER schemes for NTPS
|
18.59
|
|
WPT & BC
|
ASDC for OBC
|
Issue of
block guarantee for availing loan from NBCFDC
|
2.00
|
|
AH &
Veterinary
|
ALPCO
|
Release of
fund for implementation of VRS
|
2.12
|
|
16.03.2004
|
PIB
|
Industries
|
ATC
|
Ex-post
facto approval on release of fund
|
7.30
|
|
Co-operation
|
APOL
|
Issue of
Govt. guarantee for availing working capital
|
3.00
|
|
Injection
of additional share capital
|
1.43
|
|
Conversion
of State Govt. loan to equity
|
2.50
|
|
Irrigation
|
ASMIDC
|
Cost of
closure of the Company
|
1.20
|
|
Fisheries
|
AFDC
|
Implementation
of VRS
|
0.42
|
|
Hill Areas
|
ASHIDC
|
Implementation
of VRS
|
0.50
|
|
Investment
in capital assets
|
Not approved
|
|
3
|
8
|
10
|
15
|
238.40
|